Copper and PEX repiping

Commercial

Commercial and Multifamily Repiping in the South Bay

Repiping occupied apartment, HOA, and commercial buildings across the South Bay — phased by riser, with tenant notice and no lost operating days.

Why plumbing

The Constraint Is Occupancy, Not Plumbing

Repiping an apartment building is not a larger version of repiping a house. The pipe work is the straightforward part. The difficulty is that people live there, the building has habitability obligations that do not pause for construction, and every hour of water-off has to be scheduled, noticed, and honored.

So the program is built backwards from occupancy. We replace riser by riser rather than building-wide, which means the majority of units hold service at any given moment and the property never loses an operating day. Each unit gets a posted water-off window, and the unit is back in service the same day.

A contractor who quotes a multifamily repipe as a single building-wide shutdown is quoting a job that either will not happen or will happen at the owner's cost in tenant concessions.

Why South Bay Buildings Are Reaching This Point Together

A large share of the South Bay's apartment stock went up between the 1950s and the early 1970s — Torrance, San Pedro, Harbor City, and the older parts of Redondo Beach in particular. That construction was plumbed in galvanized steel, which corrodes from the inside and loses flow long before it leaks. Buildings from that era are now well past the material's service life, and they are arriving there at roughly the same time.

The complicating factor is partial work. Almost every building of that age has had something done somewhere — a riser replaced after a failure in the 1990s, a unit repiped during a renovation, a section of copper joined to original galvanized. Those junctions between dissimilar metals corrode faster than either material alone.

This is why we scope per unit rather than per building. A survey that samples two apartments and multiplies by unit count will be wrong, and the correction arrives as change orders.

Scope Written Per Unit, Not Per Building

Before pricing, we survey risers and in-unit conditions, check static pressure at the top floor — where any supply problem shows first — and identify where previous work has left mixed materials.

The output is a scope defined unit by unit. Owners and boards can then see what is actually being done where, and are not negotiating additions one apartment at a time once walls are open. For an HOA in particular, that document is what lets a board approve a number that holds.

How the Number Is Built

Multifamily repipes price per unit against a surveyed scope, not per square foot and not per door before anyone has been inside.

Fixture count drives it. As general orientation, repipe work runs roughly $650–$1,500 per fixture, which is why a building of one-bedrooms and a building of two-bedrooms with the same unit count carry materially different numbers. Risers, common-area mains, permit and plan check, and drywall restoration are scoped as separate lines rather than folded into a per-unit average.

Owners and boards should insist those lines are broken out by every bidder. The item most often missing is drywall restoration — a bid that ends at the plumbing leaves a second trade to be scheduled behind it, and on a property where units turn regularly that gap is measured in lost rent rather than in drywall.

Permits and Plan Check

A permit is required to replace water piping, and multi-unit scopes commonly draw a plan check rather than going over the counter. That review time sits before work can start and we treat it as a scheduled phase.

Torrance moved to fully digital plan and permit submittal in January 2026, which is a change in how the submittal is made rather than in what is required. We carry the rough and final inspections; the rough is the one that matters, because it happens while the lines are still open and visible.

Restoration and Turnover

Access openings are patched, textured, and left paint-ready as part of our scope. On a property where units turn regularly this is not a detail — a unit waiting on a separate drywall contractor is a unit that cannot be re-let on schedule, and that cost lands on the owner rather than the plumber.

We hand as-builts to management at completion so the maintenance file reflects what is actually in the walls, which is exactly the information the next contractor will not otherwise have.

Repiping a single-family home is a different exercise with a different sequence — see our residential repiping page.

What you get

Everything we deliver.

  • 01

    Phased riser-by-riser replacement

    The building keeps operating. We isolate and replace one riser at a time so the majority of units hold water service throughout, rather than shutting the property down.

  • 02

    Tenant notice and coordination

    Written notice per unit, posted water-off windows, and a schedule property management can distribute. Habitability obligations do not pause for construction.

  • 03

    Common-area and unit-side scope

    Mains, risers, branch lines, and in-unit supply. Scope is defined per unit up front so owners are not negotiating change orders one apartment at a time.

  • 04

    Permit, plan check, and inspection

    Permit pulled and rough and final inspections carried. Multi-unit scopes commonly draw a plan check rather than an over-the-counter permit — we build that into the program.

  • 05

    Restoration to a lettable standard

    Access openings patched, textured, and left paint-ready so units can turn without a second trade being scheduled behind us.

How we run it

Scope to sign-off.

  1. 01

    Survey and unit-by-unit scope

    Inspect risers and in-unit conditions, check static pressure at the top floor, and identify where previous partial work has left mixed materials. Scope written per unit, not per building average.

  2. 02

    Permit and program

    Permit and any plan check with the relevant jurisdiction, and a phasing program agreed with ownership and management before a single unit is disturbed.

  3. 03

    Phased execution

    Riser by riser. Notice issued, water off inside the posted window, unit restored the same day. The building does not lose an operating day.

  4. 04

    Inspection, restoration, handover

    Rough and final inspection, pressure test, flush, drywall restoration to paint-ready, and as-builts handed to management for the maintenance file.

Why DECOMA

One license, three disciplines, forty years.

Family-run South Bay general contractor since 1978. We design, build, and manage — under one license — so the team you start with is the team that hands you keys and the team that answers the phone when something needs fixing in year ten.

Years building
48+
Projects delivered
3,000+
Repeat clients
300+
CSLB Class
A/B

FAQ

Common questions.

Can the building stay occupied during a repipe?
Yes, and on multifamily it effectively has to. We phase riser by riser with posted water-off windows, so most units keep service while one section is being replaced. Tenants are not relocated and the property does not lose operating days.
How is a commercial repipe scoped differently from a house?
Two ways. Scope is written per unit rather than as a building average, because a 1962 building has almost always had partial work done somewhere and the conditions differ unit to unit. And the program is built around tenant notice and habitability obligations, which drive the schedule as much as the plumbing does.
Does a multifamily repipe need a plan check?
Frequently, yes. A single-family repipe often goes over the counter; multi-unit scopes commonly draw a plan check instead, which adds review time before work can start. We treat that as a scheduled phase rather than a surprise.
How is a multifamily repipe priced?
Per unit against a surveyed scope, not per square foot. Fixture count is the main driver — as general orientation, repipe work tends to run roughly $650–$1,500 per fixture, so a one-bedroom with four fixtures and a two-bedroom with seven price very differently. Risers, common-area mains, permit and plan check, and drywall restoration are scoped separately from the in-unit work. We price from a survey; a per-door number quoted before anyone has looked inside the units will not hold.
What gets left out of repipe bids on apartment buildings?
Drywall restoration is the big one — a bid that stops at the plumbing leaves you scheduling a second trade behind it, which on a turnover-sensitive property costs real rent. After that: permit and plan-check time, common-area and riser work as distinct from in-unit work, and any water main between the meter and the building. Ask every bidder to break those out or you are not comparing like with like.
Copper or PEX for an apartment building?
Both are code-legal. PEX runs with fewer joints and is faster to install through occupied structure, which shortens the window each unit is disturbed. Type L copper remains a common specification for risers. On mixed buildings we often specify differently for risers than for in-unit branch lines.
What happens to the drywall in tenant units?
Access openings are patched, textured, and left paint-ready as part of our scope. On turnover-sensitive properties this matters — a unit that needs a separate drywall contractor scheduled behind the plumber is a unit that cannot be re-let on time.
How do you handle notice to tenants?
We provide the schedule and per-unit water-off windows in a format management can distribute directly, far enough ahead to satisfy notice requirements. Coordinating that is part of the job; owners should not be reverse-engineering a construction schedule into tenant letters.

Service areas

Plumbing across the South Bay.

Born in Harbor City, working across LA County since 1978. Same crew, same license number, same shop at 25941 Frampton Ave, Harbor City.

Talk to a contractor

Tell us about your project.

One business day for a scope, timeline, and budget range. CSLB #375508 A/B.