Commercial and Multifamily Repiping in the South Bay
Repiping occupied apartment, HOA, and commercial buildings across the South Bay — phased by riser, with tenant notice and no lost operating days.
Why plumbing
The Constraint Is Occupancy, Not Plumbing
Repiping an apartment building is not a larger version of repiping a house. The pipe work is the straightforward part. The difficulty is that people live there, the building has habitability obligations that do not pause for construction, and every hour of water-off has to be scheduled, noticed, and honored.
So the program is built backwards from occupancy. We replace riser by riser rather than building-wide, which means the majority of units hold service at any given moment and the property never loses an operating day. Each unit gets a posted water-off window, and the unit is back in service the same day.
A contractor who quotes a multifamily repipe as a single building-wide shutdown is quoting a job that either will not happen or will happen at the owner's cost in tenant concessions.
Why South Bay Buildings Are Reaching This Point Together
A large share of the South Bay's apartment stock went up between the 1950s and the early 1970s — Torrance, San Pedro, Harbor City, and the older parts of Redondo Beach in particular. That construction was plumbed in galvanized steel, which corrodes from the inside and loses flow long before it leaks. Buildings from that era are now well past the material's service life, and they are arriving there at roughly the same time.
The complicating factor is partial work. Almost every building of that age has had something done somewhere — a riser replaced after a failure in the 1990s, a unit repiped during a renovation, a section of copper joined to original galvanized. Those junctions between dissimilar metals corrode faster than either material alone.
This is why we scope per unit rather than per building. A survey that samples two apartments and multiplies by unit count will be wrong, and the correction arrives as change orders.
Scope Written Per Unit, Not Per Building
Before pricing, we survey risers and in-unit conditions, check static pressure at the top floor — where any supply problem shows first — and identify where previous work has left mixed materials.
The output is a scope defined unit by unit. Owners and boards can then see what is actually being done where, and are not negotiating additions one apartment at a time once walls are open. For an HOA in particular, that document is what lets a board approve a number that holds.
How the Number Is Built
Multifamily repipes price per unit against a surveyed scope, not per square foot and not per door before anyone has been inside.
Fixture count drives it. As general orientation, repipe work runs roughly $650–$1,500 per fixture, which is why a building of one-bedrooms and a building of two-bedrooms with the same unit count carry materially different numbers. Risers, common-area mains, permit and plan check, and drywall restoration are scoped as separate lines rather than folded into a per-unit average.
Owners and boards should insist those lines are broken out by every bidder. The item most often missing is drywall restoration — a bid that ends at the plumbing leaves a second trade to be scheduled behind it, and on a property where units turn regularly that gap is measured in lost rent rather than in drywall.
Permits and Plan Check
A permit is required to replace water piping, and multi-unit scopes commonly draw a plan check rather than going over the counter. That review time sits before work can start and we treat it as a scheduled phase.
Torrance moved to fully digital plan and permit submittal in January 2026, which is a change in how the submittal is made rather than in what is required. We carry the rough and final inspections; the rough is the one that matters, because it happens while the lines are still open and visible.
Restoration and Turnover
Access openings are patched, textured, and left paint-ready as part of our scope. On a property where units turn regularly this is not a detail — a unit waiting on a separate drywall contractor is a unit that cannot be re-let on schedule, and that cost lands on the owner rather than the plumber.
We hand as-builts to management at completion so the maintenance file reflects what is actually in the walls, which is exactly the information the next contractor will not otherwise have.
Repiping a single-family home is a different exercise with a different sequence — see our residential repiping page.
What you get
Everything we deliver.
- 01
Phased riser-by-riser replacement
The building keeps operating. We isolate and replace one riser at a time so the majority of units hold water service throughout, rather than shutting the property down.
- 02
Tenant notice and coordination
Written notice per unit, posted water-off windows, and a schedule property management can distribute. Habitability obligations do not pause for construction.
- 03
Common-area and unit-side scope
Mains, risers, branch lines, and in-unit supply. Scope is defined per unit up front so owners are not negotiating change orders one apartment at a time.
- 04
Permit, plan check, and inspection
Permit pulled and rough and final inspections carried. Multi-unit scopes commonly draw a plan check rather than an over-the-counter permit — we build that into the program.
- 05
Restoration to a lettable standard
Access openings patched, textured, and left paint-ready so units can turn without a second trade being scheduled behind us.
How we run it
Scope to sign-off.
01
Survey and unit-by-unit scope
Inspect risers and in-unit conditions, check static pressure at the top floor, and identify where previous partial work has left mixed materials. Scope written per unit, not per building average.
02
Permit and program
Permit and any plan check with the relevant jurisdiction, and a phasing program agreed with ownership and management before a single unit is disturbed.
03
Phased execution
Riser by riser. Notice issued, water off inside the posted window, unit restored the same day. The building does not lose an operating day.
04
Inspection, restoration, handover
Rough and final inspection, pressure test, flush, drywall restoration to paint-ready, and as-builts handed to management for the maintenance file.
Why DECOMA
One license, three disciplines, forty years.
Family-run South Bay general contractor since 1978. We design, build, and manage — under one license — so the team you start with is the team that hands you keys and the team that answers the phone when something needs fixing in year ten.
- Years building
- 48+
- Projects delivered
- 3,000+
- Repeat clients
- 300+
- CSLB Class
- A/B
FAQ
Common questions.
Can the building stay occupied during a repipe?
How is a commercial repipe scoped differently from a house?
Does a multifamily repipe need a plan check?
How is a multifamily repipe priced?
What gets left out of repipe bids on apartment buildings?
Copper or PEX for an apartment building?
What happens to the drywall in tenant units?
How do you handle notice to tenants?
Service areas
Plumbing across the South Bay.
Born in Harbor City, working across LA County since 1978. Same crew, same license number, same shop at 25941 Frampton Ave, Harbor City.